Wuhan Tianma 6G OLED line installation delay
The Tianma T4 plant in Wuhan has continued to produce even during the corona period, and the core equipment of the ph2 6G OLED line has already been brought in, but the equipment set-up is delayed due to the inability of overseas equipment companies to enter Wuhan.
In recent, as the number of corona virus spreaders in China, including Wuhan, has declined, equipment set-up is expected to resume from the second quarter, and mass production is expected to start after the third quarter.
The ph2 of Tianma T4 was signed on June 1, 2018, and a total of RMB 14.5 billion was invested. When the Ph2 setup is complete, the Tianma T4 plant will have a total of 35K Capa in 6G.